German grid bottlenecks growing hurdle for investment and energy transition
Handelsblatt
Companies applying for electricity grid connections in many regions across Germany increasingly face long delays or even rejections, as network operators struggle with rapidly growing demand, reported business daily Handelsblatt. The rejection of large-scale consumers, such as industrial companies, is a disadvantage for Germany as a place to do business and threatens the energy transition's progress, the newspaper wrote.
Grid operators, regional governments and businesses across the country are facing challenges when it comes to allocating new connections, the newspaper said. This includes projects in the northern city of Hamburg, where the local network company currently rejects all requests that exceed the capacity needed for two electric truck charging points. Tesa, a manufacturer of adhesive tape headquartered near Hamburg, told the newspaper that its expansion plans were rejected because of grid bottlenecks. Plans for a low-emission industrial park in the western German town of Rommerskirchen are delayed at least into the mid-2030s, Handelsblatt wrote.
“It’s quite irritating when you’re in a country that is an industrial nation, that wants to play among the leaders, and then you’re told: a grid connection might be available in 20 years,” the newspaper quotes Microsoft’s Germany chief Agnes Heftberger as saying.
A spokesperson for German utility group E.ON told Handelsblatt that grid connection demands have grown beyond expectations. “Since 2020, demand for grid connections has grown at a pace and on a scale that no one could have reasonably predicted.”
Moving away from fossil fuels by electrifying all sectors of the economy is seen as key to a successful transition to climate neutrality, though only if the added electricity is clean. At the UN climate change conference COP31 in Turkey, governments from across the world are debating a collective global target to increase the share of final energy demand met by electricity from just over 20 percent today to 35 percent by 2035.
However, grid expansion has long been a major obstacle to electrification, and both the EU and Germany are working on policies to address this, at both the transmission and the distribution grid level. With its Grid Package, the European Commission aims to tackle structural challenges by bringing a European perspective to planning, strengthening interconnectivity, and supporting the rapid electrification of transport, heating, and industry.