Germany should make better use of its distribution grids and speed up their expansion, a broad coalition of 14 associations representing the energy sector and electricity consumers said in a joint appeal, as the government prepares a distribution grid package. 

Distribution grids, which connect consumers locally with the power system, are “increasingly becoming an obstacle to the transformation of the economy,” said the group, which includes the renewables association BEE, the German Engineering Federation (VDMA) and the energy-intensive business association VIK.

Germany’s economy ministry has pledged to draft a policy package to speed up the expansion of the electricity distribution grid by the end of the year to accelerate their expansion, with the aim of halving the time it takes to complete projects. While discussions have started, there are no details on the package yet, business daily Handelsblatt reported.

While Germany has made progress in accelerating permitting for renewable energy projects, grids have lagged behind, with measures to improve network utilisation and speed up expansion having only a limited effect so far, the group said. Bottlenecks in distribution grids are increasingly slowing Germany’s electrification, with battery projects, data centres, industry electrification projects, and car charging infrastructure often delayed for a lack of grid connections, the group argued.

“Expanding the grid alone is not enough,” said Sebastian Bolay, head of energy, environment and industry at the chamber of commerce DIHK. “We must also use the existing grids more intelligently and efficiently at the same time.”

To overcome this, the group argued, Germany could allow customers to exceed their contracted connection capacity or introduce industrial flexible grid tariffs. It could also let operators chose between underground and overhead lines or plan and secure land for substations in advance.

Germany has over 800 distribution grid operators, which connect users such as households, industry, heat pumps and electric vehicles, as well as wind, solar plants and batteries, to the power system. Grids have not kept pace with the rapid expansion of renewables and a surge in connection requests from batteries, data centres and industry. Companies in many regions now face long delays or even rejections, Handelsblatt reported earlier this month

Insufficient distribution grid capacity and faulty regulatory processes are holding back the roll-out of renewable energy and storage projects across Europe, according to a report commissioned by environmental NGO Beyond Fossil Fuels. The report found that 375 gigawatts (GW) of renewable energy projects and 455 GW of battery storage projects across eight European countries had submitted a distribution grid connection request but were still awaiting approval.

All texts created by the Clean Energy Wire are available under a “Creative Commons Attribution 4.0 International Licence (CC BY 4.0)”. They can be copied, shared and made publicly accessible by users so long as they give appropriate credit, provide a link to the license, and indicate if changes were made.

Ask CLEW

Researching a story? Drop CLEW a line for background material and contacts.

Get support

Journalism for the energy transition

Up